Major pumping station upgrade scheme expanded to lower flood risks in the Broads

25 0
11.09.2026

The Broads Internal Drainage Board (IDB) has agreed to bring forward the replacement of Repps Pumping Station into its wider Upper Thurne Integrated Drainage Improvement Project.

This expansion will see four pumping stations delivered as part of the current phase of the project, with construction work already "well under way" in Martham, Potter Heigham and Brograve.

The IDB says this is a "major programme of investment to replace or refurbish pumping stations whose infrastructure has, in many cases, significantly exceeded its original design life".

It already reached a key milestone earlier this year with the commissioning of new pumps at Horsey and St Benet’s - the first completed upgrades in the........