Plastic-busting test plant given green light
Swift Technology Group is building the trial facility, which uses a process called pyrolysis to break down plastics.
The company was first granted permission in December 2023, but delays with specialist parts meant more time was needed.
Design plans for the pyrolysis plant (Image: NNDC) North Norfolk District Council has now agreed to extend the permission from 18 months to two years.
However, the plant will still only be allowed to run for 60 days in total - 30 days for commissioning........